If a FIDIC Red, Yellow, or Silver Book (edition 2017) is applied, in which of the following two cases is the Contractor required to submit a revised programme?
Choose all of the correct answers (multiple possibilities).
A.
The Contractor shall revise the Programme only by request from the Engineer or the Employer (in case of FIDIC Silver Book).
B.
To accurately reflect the actual progress of the Works, but only if any Programme ceases to reflect actual progress with at least 42 days.
C.
To accurately reflect the actual progress of the Works, whenever any Programme ceases to reflect actual progress or is otherwise inconsistent with the Contractor's obligations.
D.
Upon a request from the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) notifying it that the Programme fails to comply with the Contract, to a specified extent, or no longer reflects actual progress or is otherwise inconsistent with the Contractor's obligations.
Option C is correct: The Contractor must revise the programme whenever it no longer accurately reflects progress or obligations.
Option D is correct: The Contractor must also revise the programme upon formal request if it fails contract compliance or progress reflection.
Option A is incorrect; the Contractor has ongoing obligations beyond formal requests.
Option B is incorrect; no 42-day threshold applies in the contract for revision.
[References:, , FIDIC Red, Yellow, Silver Books 2017 Edition, Sub-Clause 8.3 – Programme, , FIDIC Contract Manager Study Guide, Module on Programme and Delay Management]