Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?
Choose all of the correct answers (multiple possibilities)
Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)
Choose all of the correct answers (multiple possibilities).
(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)
Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)
Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)
(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)
(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)
Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?