Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the FIDIC Contract Manager CCM Questions and answers with CertsForce

Viewing page 2 out of 5 pages
Viewing questions 11-20 out of questions
Questions # 11:

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)

Options:

A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.


B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor ' s Cost.


C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor ' s items on the Site.


D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor ' s items on the Site if the Contractor fails, as this is the Contractor ' s obligation.


Expert Solution
Questions # 12:

Under the FIDIC Construction Contract (Red Book), which of the following amendments do NOT comply with the FIDIC Golden Principles? [1999 Edition] (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The Contractor is responsible for the performance of the Nominated Subcontractors


B.

Deletion of Sub-Clauses 20.2 - 20.4 for a Project constructed in United Arab Emirates


C.

The DAB Decision is final and binding


D.

The Payment shall be released by the Employer within 180 days calculated from receiving the Contractor ' s Monthly Statement


Expert Solution
Questions # 13:

(The Employer is a leading company in the hospital and medical care sector who wishes to build a new hospital. The Employer is considering approaching a financial institute to secure most of the funds; therefore, he requires clarity and stability in terms of the Project ' s budget and time for completion. Which book do you recommend?)

Options:

A.

Red Book


B.

Yellow Book


C.

Silver Book


D.

All the above


Expert Solution
Questions # 14:

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:

A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.


B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.


C.

Yes, because otherwise the Contractor doesn ' t have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.


D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor ' s Documents in the Employer ' s Requirements, as stated in Sub-Clause 5.2.


Expert Solution
Questions # 15:

Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then ... [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies)

Options:

A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.


B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.


C.

The Contractor cannot proceed in accordance with the Programme.


D.

The Engineer is deemed to have no objection to use the revised programme submitted by the Contractor, for the Works.


Expert Solution
Questions # 16:

(If a Section or Part has been taken-over but the Taking-Over Certificate has not been issued for the Works, the Engineer has the right to instruct a Variation to that Section/Part. Is this statement true or false?)

Options:

A.

True


B.

False


Expert Solution
Questions # 17:

(You are the Contract Manager in a contract using the FIDIC Red Book with a Dispute Avoidance and Adjudication Board. The DAAB is already appointed (standing DAAB). You are coaching your team on the steps to be followed to request for informal assistance from the DAAB during a Site visit. Which one of the following does NOT belong to those steps?)

Options:

A.

The Employer and the Contractor have identified an issue and disagreement, and have agreed between themselves that they want the DAAB to provide assistance and/or informally discuss and attempt to resolve that issue/disagreement.


B.

The Engineer has made a non-objection letter, in which it is stated that the issue/disagreement does not concern the matter that is being dealt with by the Engineer.


C.

The Employer and the Contractor have made a " joint request " in writing before the DAAB gives the requested assistance.


D.

Both Parties should be present at the meeting in which the DAAB provides assistance.


Expert Solution
Questions # 18:

Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 19:

You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?

Options:

A.

Both you and Y are both correct.


B.

You are correct, Y is wrong.


C.

You are wrong, Y is correct.


D.

Both you and Y are wrong.


Expert Solution
Questions # 20:

When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition 1999)?

Options:

A.

Without undue delay after the issuance of the Taking-Over Certificate.


B.

Without undue delay after the issuance of the Performance Certificate.


C.

Within 21 days after the issuance of the Taking-Over Certificate.


D.

Within 21 days after the issuance of the Performance Certificate.


Expert Solution
Viewing page 2 out of 5 pages
Viewing questions 11-20 out of questions