The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP's)?


A.

GP 3


B.

GP 1


C.

GP 2


D.

GPA