FIDIC Certified Contract Manager CCM Question # 20 Topic 3 Discussion

FIDIC Certified Contract Manager CCM Question # 20 Topic 3 Discussion

CCM Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

Under the FIDIC Red Book (edition 2017), if the Contractor fails to comply with Site clearance obligation, what two options does the Employer have?

Choose all of the correct answers (multiple possibilities)


A.

The Employer may sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.


B.

The Engineer cannot sell or otherwise dispose any remaining items and reinstate the Site at the Contractor's Cost.


C.

The Employer is entitled to the cost of reinstating, clearing the Site and disposal cost to the extent they exceed the money received from selling the remaining Contractor's items on the Site.


D.

The Employer cannot reinstate and clear the Site and dispose the remaining Contractor's items on the Site if the Contractor fails, as this is the Contractor's obligation.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.