FIDIC Certified Contract Manager CCM Question # 13 Topic 2 Discussion

FIDIC Certified Contract Manager CCM Question # 13 Topic 2 Discussion

CCM Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?


A.

When the works are simple and of short duration.


B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.


C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.


D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.