Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

FIDIC Certified Contract Manager CCM Question # 14 Topic 2 Discussion

FIDIC Certified Contract Manager CCM Question # 14 Topic 2 Discussion

CCM Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)


A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.


B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.


C.

Yes, because otherwise the Contractor doesn ' t have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.


D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor ' s Documents in the Employer ' s Requirements, as stated in Sub-Clause 5.2.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.