Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the FIDIC Contract Manager CCM Questions and answers with CertsForce

Viewing page 3 out of 5 pages
Viewing questions 21-30 out of questions
Questions # 21:

(Which two statements are correct for the FIDIC Red Book (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Contract includes the General Conditions and Particular Conditions, and no other documentation.


B.

Conditions of Contract means these General Conditions as amended by Particular Conditions.


C.

Contract Data is part of General Conditions of Contract.


D.

Contract Agreement, Letter of Acceptance and Letter of Tender are part of the Contract.


Expert Solution
Questions # 22:

A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months. This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?

Options:

A.

If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.


B.

The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.


C.

In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.


D.

If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.


Expert Solution
Questions # 23:

In which one of the following circumstances is it recommended to select the Contractor after a two-stage procurement procedure (pre-qualification + tender procedure)?

Options:

A.

When the works are simple and of short duration.


B.

When there is a limited number of capable experienced contractors available and ready to take part in the procurement.


C.

In case of large scale works, where there are several companies likely to have an interest in submitting an offer.


D.

If there is international financing for the project, it is always necessary to conduct a two-stage procurement procedure.


Expert Solution
Questions # 24:

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

Options:

A.

The Commencement Date


B.

The date of the Taking Over Certificate


C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate


D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates


Expert Solution
Questions # 25:

Under the FIDIC Red and Yellow Books (edition 1999): if the Engineer gives an instruction which requires the Employer ' s prior approval, the Contractor is required to verify whether the Engineer has obtained the Employer ' s prior approval or not. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 26:

(In a region experiencing civil unrest and armed conflict under a FIDIC Red Book 1999 Contract, violence escalates into an insurrection, forcing the Contractor to stop work and retreat to a secured compound. The Contractor issues a notice claiming this is an Employer’s Risk under Sub-Clause 17.3 (a) and (b), requesting Extension of Time and Cost. What is the most appropriate position for the Engineer at this stage?)

Options:

A.

This is an Employer’s Risk under Sub-Clause 17.3 (a)/(b), and the Contractor is entitled to EOT and Cost. The Engineer will assess actual entitlement after the event; no further notices are required.


B.

Violence is an Employer’s Risk; however, the Contractor can only claim after the situation ends. The Engineer cannot determine EOT or Cost yet, and the Contractor must submit a fully detailed claim later.


C.

The Contractor should have foreseen such risks due to the region’s history; therefore, Clause 19 is not applicable.


D.

The Employer is in breach of its obligation to provide safe working conditions under Sub-Clause 2.1; therefore, the Contractor can claim on that basis.


Expert Solution
Questions # 27:

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.


B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.


C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.


D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.


Expert Solution
Questions # 28:

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.


B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.


C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.


D.

Receipt of a statement and supporting documents.


Expert Solution
Questions # 29:

Which of the following statements are relevant to continuing effect claims? [FIDIC 2017 Edition]

(2 correct answers apply)

Options:

A.

Continuing effect claims shall be noticed in the same way as " normal " claims, within 28 days after the Claiming Party became aware of the event or circumstance.


B.

In case the Employer is the Claiming Party, then he/she is not obliged to submit interim claims.


C.

In case the Contractor is the Claiming Party, when he/she misses to submit even just a single interim claim, then his/her entitlement is lost.


D.

In general, a fully detailed Claim has to be submitted within 84 days after becoming aware of the event giving rise to the claim.


Expert Solution
Questions # 30:

Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.


B.

The dayworks related Sub-Clause is also applicable to other types of works.


C.

The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.


D.

The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that " a Variation shall " be executed on a daywork basis.


Expert Solution
Viewing page 3 out of 5 pages
Viewing questions 21-30 out of questions