FIDIC Certified Contract Manager CCM Question # 24 Topic 3 Discussion

FIDIC Certified Contract Manager CCM Question # 24 Topic 3 Discussion

CCM Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities)


A.

In case the Engineer refuses to issue a Performance Certificate or to issue one with a correct date under Sub-Clause 11.9, and the Contractor has disagreed with the requested entitlement or relief in connection with this refusal, Dispute shall be deemed to have arisen.


B.

If a Party is dissatisfied with the determination and has given Notice of Dissatisfaction (NOD) to the other party within a strict 28-day time limit, a Dispute arises and either Party may proceed under Sub-Clause 21.4 to obtain a DAAB decision on it.


C.

The Dispute must be submitted to the Dispute Avoidance and Adjudication Board (DAAB) within 42 days, otherwise the NOD is deemed to have lapsed and is no longer valid.


D.

Both 'Disagreement' and 'Dispute' are defined terms under the Conditions of Contract.