Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

FIDIC Certified Contract Manager CCM Question # 28 Topic 3 Discussion

FIDIC Certified Contract Manager CCM Question # 28 Topic 3 Discussion

CCM Exam Topic 3 Question 28 Discussion:
Question #: 28
Topic #: 3

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).


A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.


B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.


C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.


D.

Receipt of a statement and supporting documents.


Get Premium CCM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.