FIDIC Certified Contract Manager CCM Question # 27 Topic 3 Discussion

FIDIC Certified Contract Manager CCM Question # 27 Topic 3 Discussion

CCM Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

(Which two of the following items are new features introduced in FIDIC Red and Yellow Books (edition 2017) in respect to the procedures relating to the Programme?

Choose all of the correct answers (multiple possibilities).)


A.

The requirement to submit a revised programme by the Contractor whenever the previous programme is inconsistent with actual progress.


B.

Specifying the programming software that shall be used by the Contractor in preparation of the Programme.


C.

The requirement that any revised programmes to be submitted by the Contractor is to reflect accurately the actual progress of the works.


D.

Submission by the Contractor of a detailed time Programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1.