Questions # 31:

You are teaching a group of early career professionals in the Contract Management department about the FIDIC 2017 Rainbow Suite of contract, and you are explaining about the intention of Delay Damages. Which one of the following statements is correct?

Options:

A.

Delay Damages is intended to provide full compensation to the Employer for all damages that it is expected to suffer as a result of the delay.


B.

Delay Damages is intended to be treated as an incentive for the Contractor to perform on time.


C.

Delay Damages is not intended to remove burden for the Employer to demonstrate and prove that it has suffered any loss or damage.


D.

None of the above.


Expert Solution
Questions # 32:

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.


B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.


C.

There is never a difference in effect whether in the Particular Conditions when the term " Works " is used, or when the term " works " is used.


D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.


Expert Solution
Questions # 33:

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance


B.

Letter of Intent


C.

Memorandum of understanding


D.

Letter of Intent & Memorandum of understanding


Expert Solution
Questions # 34:

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 35:

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.


B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.


C.

Any amounts to be added and deducted for changes in legislation and changes in cost.


D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.


Expert Solution
Questions # 36:

Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 37:

Which one of the following is NOT considered a change made in the 2017 edition of the FIDIC Red, Yellow, and Silver Books?

Options:

A.

The concentration on dispute avoidance, including an enhanced role for the Dispute Avoidance and Adjudication Board (DAAB) in this respect, and promoting cooperation between the parties during the project.


B.

New procedures requiring the Contractor to prepare and implement a Quality Management System to show compliance with the Contract requirements.


C.

A fair and balanced approach where risk is allocated to the Party that is best able to bear and control that risk.


D.

New procedures requiring the Contractor to prepare and implement a Compliance Verification System to show that the design, materials, workmanship and certain other matters all comply.


Expert Solution
Questions # 38:

Under the FIDIC Red, Yellow, and Silver Books (edition 2017), if a Dispute is referred to the Dispute Avoidance and Adjudication Board (DAAB) to obtain its decision, the Parties shall suspend performing their obligations in accordance with the Contract, until they receive further directions from the DAAB. Is this statement true or false?

Options:

A.

True


B.

False


Expert Solution
Questions # 39:

(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)

Options:

A.

True


B.

False


Expert Solution
Questions # 40:

(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))

Options:

A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.


B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.


C.

The Contractor cannot proceed in accordance with the Programme.


D.

The Engineer is deemed to have no objection to use the revised Programme for the Works.


Expert Solution