Regarding the FIDIC Silver Book (both editions), if a part of the Works is to be paid according to quantity supplied or work done, appropriate provisions must be included in the Particular Conditions. Is this statement true or false?
This statement is true. The Silver Book (EPC/Turnkey contracts) usually involves lump-sum payment, but if part payment is based on quantity or work done, this must be explicitly provided for in the Particular Conditions to avoid ambiguity.
Such provisions ensure clarity on payment terms in line with project specifics.
[References:, , FIDIC Silver Book 1999 & 2017 Editions, Sub-Clause 14 – Payment Provisions, , FIDIC Contract Manager Study Guide, Module on Payment Procedures, ]