FIDIC Certified Contract Manager CCM Question # 40 Topic 5 Discussion

FIDIC Certified Contract Manager CCM Question # 40 Topic 5 Discussion

CCM Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

(Upon review of the revised programme, submitted by the Contractor, if the Engineer (under FIDIC Red or Yellow Books) or Employer (under FIDIC Silver Book) does not give a Notice of Non-Compliance within 14 days after receiving a revised programme, then… [complete the sentence, thereby considering FIDIC Red, Yellow, and Silver Books (edition 2017)]. (1 correct answer applies))


A.

The Contractor shall submit a Notice to the Engineer or the Employer reminding him to give its approval on the revised programme.


B.

The Engineer shall be deemed to have given a Consent and the revised programme shall be the Programme.


C.

The Contractor cannot proceed in accordance with the Programme.


D.

The Engineer is deemed to have no objection to use the revised Programme for the Works.