Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 8 out of 11 pages
Viewing questions 71-80 out of questions
Questions # 71:

Which of the following best describes the difference between the current state and the desired future state in project management?

Options:

A.

The current state is a high-level view of the project scope, and the desired state is what is happening right now.


B.

The current state is where the business is now, and the desired state is where the project is going to take the business.


C.

The current state is a high-level view of the project scope, and the desired future state is the specific outcome the business wants.


D.

The current state defines the specific outcome the business wants, and the desired state documents what is happening now that prevents it.


Expert Solution
Questions # 72:

A development team, which is working on a software project demonstrates software functionality 10 project stakeholder a week before the implementation date. Several stakeholders comment that the software does not meet the communicated expectations. Which of the following tools should the project manager use to validate the functionality?

Options:

A.

Project status report


B.

Requirements Traceability Matrix


C.

Detect log


D.

Signed project charter


E.

Work breakdown structure


Expert Solution
Questions # 73:

During a sponsor meeting, a PM is assigned to manage a new external project for an IT consultant. The sponsor wants the PM to establish an agreement regarding the exchange of money between both parties. Which of the following documents would the PM most likely create?

Options:

A.

Business requirement


B.

Client statement of work


C.

Formal contract


D.

Project charter


Expert Solution
Questions # 74:

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

Options:

A.

Trigger the contingency plan and communicate with the stakeholders.


B.

Work with the functional managers to create a work-around.


C.

Submit a change request to the change control board.


D.

Transfer the risk by hiring a new vendor who was successful on a previous project.


E.

Set up an escalation meeting with the sponsor.


Expert Solution
Questions # 75:

How does data discovery assist with data classification'?

Options:

A.

It shows where specific data is stored


B.

It automatically classifies data by keywords


C.

It helps to identify the data owner


D.

It provides assurance of data integrity


Expert Solution
Questions # 76:

During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?

Options:

A.

Issue log


B.

Defect log


C.

Change log


D.

Task board


Expert Solution
Questions # 77:

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?

Options:

A.

Time and materials contract


B.

Master service agreement


C.

Fixed-price contract


D.

Statement of work


E.

Cost-plus agreement


Expert Solution
Questions # 78:

Several stakeholders have declined the invitation for the kickoff of a major digital transformation protect. Which of the following actions should the project manager take NEXT?

Options:

A.

Escalate directly to the project sponsor


B.

Push the kickoff meeting out by one week


C.

Proceed with the kickoff as planned


D.

Identity replacements for project stakeholders


Expert Solution
Questions # 79:

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000


B.

10 days and $3,200


C.

12 days and $3,800


D.

14 days and $4,000


Expert Solution
Questions # 80:

Which of the following are primary features provided by a standard laaS solution? (Select two).

Options:

A.

Encryption


B.

Storage


C.

Networking


D.

User interface


E.

Access


F.

Database


Expert Solution
Viewing page 8 out of 11 pages
Viewing questions 71-80 out of questions