Pass the CompTIA Project+ PK0-005 Questions and answers with CertsForce

Viewing page 4 out of 11 pages
Viewing questions 31-40 out of questions
Questions # 31:

A project team has implemented a new system and needs to ensure it is usable. Which of the following should be performed first?

Options:

A.

Provide end-user training.


B.

Decommission old systems.


C.

Release external consultants.


D.

Monitor performance.


Expert Solution
Questions # 32:

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

Options:

A.

ROI.


B.

SOW.


C.

RFI.


D.

RPR


Expert Solution
Questions # 33:

A project manager receives an escalation from an external group reporting that an expected deliverable should have been available some time ago. After analysis, the project team realizes the deliverable was provided on time. Which of the following should the project manager do next?

Options:

A.

Request a change control ticket.


B.

Review the schedule plan.


C.

Refine the project documentation.


D.

Revise the communication plan.


Expert Solution
Questions # 34:

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote


B.

Information


C.

Proposal


D.

Bid


Expert Solution
Questions # 35:

A PM needs to calculate the progress of the whole project scope for a presentation to the sponsor. Which of the following is the first document the PM should update?

Options:

A.

Project network diagram


B.

Gantt chart


C.

Issue log


D.

Risk report


Expert Solution
Questions # 36:

Which of the following best describes the role of a PM for a CRM system?

Options:

A.

To track sales


B.

To store customer information


C.

To implement new features


D.

To pay vendors


Expert Solution
Questions # 37:

Which of the following is a quantitative key performance indicator?

Options:

A.

The project sponsor ranked the graphics of an application as four out of five.


B.

The project implements the application in ten different geographical regions.


C.

The workers complete tasks on average 25% faster using a new application.


D.

The use of a multimedia interface appeals more to users under the age of 21.


Expert Solution
Questions # 38:

Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?

Options:

A.

Variable costs


B.

Fixed costs


C.

Front-loaded


D.

Time and materials


Expert Solution
Questions # 39:

As a result of lessons learned, a project manager convenes a meeting to understand the poor quality of the project documentation. During the meeting, project team members provide insights from their perspectives and discussions with group members. Which of the following is the project team doing?

Options:

A.

Executing the approved contingency plan


B.

Constructing an Ishikawa diagram to determine the root cause


C.

Using a Pareto chart to prioritize the different causes


D.

Engaging the senior management team in regard to the issue


Expert Solution
Questions # 40:

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.


B.

Assess the resource pool.


C.

Develop a QA plan.


D.

Create RACI matrix.


Expert Solution
Viewing page 4 out of 11 pages
Viewing questions 31-40 out of questions