Questions # 21:

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW


B.

WBS


C.

RACI


D.

PERT


Expert Solution
Questions # 22:

Which of the following is a consideration when determining a project's ESG factors?

Options:

A.

Project management methodology


B.

IT infrastructure security


C.

Proper accounting practices


D.

Corporate values compliance


Expert Solution
Questions # 23:

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

Options:

A.

Synchronous


B.

Informal


C.

Asynchronous


D.

Formal


Expert Solution
Questions # 24:

Which of the following is the best example of CapEx?

Options:

A.

Taxes


B.

Vehicles


C.

Salaries


D.

Utilities


Expert Solution
Questions # 25:

During an active project, the finished product is not meeting quality specifications Which of the following actions should be taken after the project manager determines what would be needed to resolve the issues?

Options:

A.

Communicate the change status.


B.

Document change recommendations


C.

Create a change request.


D.

Implement the changes


Expert Solution
Questions # 26:

While in the closing phase of a project, the project manager gathers feedback from stakeholders. Which of the following best describes a benefit of this feedback?

Options:

A.

It highlights the performance issues of the project manager and team members.


B.

It lets the project manager know which stakeholders are allies for future projects.


C.

It helps the project manager create a more structured lessons-learned session.


D.

It identifies the stakeholders' real opinions about the project.


Expert Solution
Questions # 27:

A project manager wants to maximize the cost savings on software expenditures for a project. Currently, the project manager does not know how many users will acquire the product. Which of the following procurement methods should the project manager pursue?

Options:

A.

Build


B.

Subscription


C.

Lease


D.

Buy


Expert Solution
Questions # 28:

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?

Options:

A.

Rational Unified Process


B.

Waterfall


C.

Agile


D.

DevOps


Expert Solution
Questions # 29:

A project manager is responsible for implementing a large, centralized repository that stores raw information from various sources in a structured and organized way. Which of the following should the project manager implement?

Options:

A.

Shared folder


B.

Infrastructure


C.

Multitiered architecture


D.

Data warehouse


Expert Solution
Questions # 30:

A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

Options:

A.

Issue log


B.

Gantt chart


C.

Milestone chart


D.

Change control log