Questions # 101:

Which of the following artifacts should project team members use if they want to identify who to communicate with and at what level?

Options:

A.

Concept of operations


B.

WBS


C.

Integrated master schedule


D.

RACI


Expert Solution
Questions # 102:

A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?

Options:

A.

ESG


B.

PHI


C.

Pll


D.

ROI


Expert Solution
Questions # 103:

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window


B.

Risk assessment


C.

Operational security


D.

Validation check


Expert Solution
Questions # 104:

A project manager is in the process of evaluating the probability and impact of a risk by assigning numbers such as a monetary value. Which of the following is the project manager using?

Options:

A.

Monte Carlo simulation


B.

Root cause analysis


C.

Quantitative risk analysis


D.

Risk response analysis


Expert Solution
Questions # 105:

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool


B.

Email


C.

Virtual meetings


D.

Enterprise CMS


Expert Solution
Questions # 106:

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram


B.

Velocity chart


C.

Control chart


D.

Fishbone diagram


Expert Solution
Questions # 107:

Which of the following tools is best to use for storing lessons learned?

Options:

A.

Whiteboard


B.

Wiki knowledge base


C.

Content management system


D.

Workflow platform


Expert Solution
Questions # 108:

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board


B.

Pareto chart


C.

Ishikawa diagram


D.

Decision tree