New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

CompTIA Project+ Certification (2025) PK0-005 Question # 105 Topic 11 Discussion

CompTIA Project+ Certification (2025) PK0-005 Question # 105 Topic 11 Discussion

PK0-005 Exam Topic 11 Question 105 Discussion:
Question #: 105
Topic #: 11

A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager Which of the following should the newly appointed project manager do next?


A.

Conduct a risk assessment.


B.

Create a project scope document


C.

Identify stakeholders


D.

Perform a lessons learned.


Get Premium PK0-005 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.