Questions # 91:

Which does NOT reflect the PRINCE2 principle of continued business justification?

Options:

A.

There must be a justifiable reason for starting a project


B.

The business justification drives decision making


C.

If a project is no longer forecast to deliver a financial benefit, it should be stopped.


D.

If a project can no longer be justified, it should be stopped


Expert Solution
Questions # 92:

Which statement about the Directing a Project process is true?

Options:

A.

Provides a mechanism for the Project Board to assure that there is continued business justification


B.

Covers the day-to-day activities of the Project Manager


C.

Ensures there are regular progress meetings


D.

Begins on completion of the Initiating a Project process


Expert Solution
Questions # 93:

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

Options:

A.

a corporate


B.

a temporary


C.

an external


D.

a technical


Expert Solution
Questions # 94:

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

Options:

A.

Only corporate or programme management


B.

Only the Project Board


C.

Only the Project Manager


D.

All levels of management


Expert Solution
Questions # 95:

Which product documents the information needed to demonstrate continued business justification?

Options:

A.

Business Case


B.

Communication Management Strategy


C.

Project Product Description


D.

Quality Management Strategy


Expert Solution
Questions # 96:

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary


B.

Managing Product Delivery


C.

Closing a Project


D.

Controlling a Stage


Expert Solution
Questions # 97:

Which is a true statement about time-driven controls?

Options:

A.

Time-driven controls are used for monitoring the progress of Work Packages and management stages


B.

Time-driven controls take place when specific events happen


C.

Time-driven controls are produced at the end of a stage


D.

An Exception Report is a time-driven control


Expert Solution
Questions # 98:

Whose approval is needed to replace a Stage Plan with an Exception Plan?

Options:

A.

Corporate or programme management


B.

Project Board


C.

Project Manager


D.

Team Manager


Expert Solution
Questions # 99:

Why is the Initiating a Project process used?

Options:

A.

To decide which project approach is suitable for the project


B.

To fully understand how the project objectives will be achieved before committing significant resources


C.

To produce the required Work Packages


D.

To enable corporate or programme management to give authorization to deliver a project


Expert Solution
Questions # 100:

In what process is the authorization to deliver the project's products given?

Options:

A.

Starting up a Project


B.

Initiating a Project


C.

Managing a Stage Boundary


D.

Directing a Project


Expert Solution