PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 92 Topic 10 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 92 Topic 10 Discussion

Prince2-Foundation Exam Topic 10 Question 92 Discussion:
Question #: 92
Topic #: 10

Which statement about the Directing a Project process is true?


A.

Provides a mechanism for the Project Board to assure that there is continued business justification


B.

Covers the day-to-day activities of the Project Manager


C.

Ensures there are regular progress meetings


D.

Begins on completion of the Initiating a Project process