PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 91 Topic 10 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 91 Topic 10 Discussion

Prince2-Foundation Exam Topic 10 Question 91 Discussion:
Question #: 91
Topic #: 10

Which does NOT reflect the PRINCE2 principle of continued business justification?


A.

There must be a justifiable reason for starting a project


B.

The business justification drives decision making


C.

If a project is no longer forecast to deliver a financial benefit, it should be stopped.


D.

If a project can no longer be justified, it should be stopped


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.