PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 90 Topic 10 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 90 Topic 10 Discussion

Prince2-Foundation Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?


A.

Configuration Item Record


B.

Quality Register


C.

Highlight Report


D.

Checkpoint Report


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.