PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 94 Topic 10 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 94 Topic 10 Discussion

Prince2-Foundation Exam Topic 10 Question 94 Discussion:
Question #: 94
Topic #: 10

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?


A.

Only corporate or programme management


B.

Only the Project Board


C.

Only the Project Manager


D.

All levels of management


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.