Question #: 97
Topic #: 10

Which is a true statement about time-driven controls?


A.

Time-driven controls are used for monitoring the progress of Work Packages and management stages


B.

Time-driven controls take place when specific events happen


C.

Time-driven controls are produced at the end of a stage


D.

An Exception Report is a time-driven control