PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 98 Topic 10 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 98 Topic 10 Discussion

Prince2-Foundation Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

Whose approval is needed to replace a Stage Plan with an Exception Plan?


A.

Corporate or programme management


B.

Project Board


C.

Project Manager


D.

Team Manager


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.