Questions # 51:

Which is a minimum requirement for applying the organization theme?

Options:

A.

The project's approach to engaging with its stakeholders must be defined


B.

Roles must be combined to reduce the number of individuals needed on the project


C.

During a procurement the senior supplier must be appointed from the customer organization


D.

The project team must change at each end stage of the project life cycle


Expert Solution
Questions # 52:

Which statement describes the context of the 'initiating a project" process?

Options:

A.

The project is viewed from the perspective of the project board in this process


B.

This process should result in key stakeholders being committed to the project


C.

This process is triggered by the assembly of the project brief


D.

The 'controlling a stage' process will start immediately after this process


Expert Solution
Questions # 53:

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval


B.

Gain project board feedback on the Issue priority


C.

Consider the impact of alternative options for resolution


D.

Determine the initial priority of the issue that has been raised


Expert Solution
Questions # 54:

Which is an objective of the 'controlling a stage' process?

Options:

A.

To review the business justification for the project


B.

To replan the current stage when directed


C.

To develop products to defined quality criteria


D.

To produce a learn plan for the work package


Expert Solution
Questions # 55:

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams


B.

Rely on regular reporting by team managers to determine whether the work Is on track


C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication


D.

Focus on publishing standard messages to key influencers throughout the project


Expert Solution
Questions # 56:

Which is a minimum requirement when applying the 'risk' theme?

Options:

A.

To identity and ring-fence an explicit risk budget within the project's budget


B.

To describe the probability impact grid in the risk management approach


C.

To appoint project assurance to maintain the risk register during initiation


D.

To assess if risks might have a material impact on business justification


Expert Solution
Questions # 57:

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.

corporate, programme management or the customer


B.

the project board


C.

the project manager


D.

the change authority


Expert Solution
Questions # 58:

Identify the missing words in the following sentence.

The 'starting up a project" process is triggered when a [ ? J is available.

Options:

A.

project business case


B.

project mandate


C.

stage plan


D.

work package


Expert Solution
Questions # 59:

Which statement about applying the 'tailor to suit the project' principle is CORRECT?

Options:

A.

PRINCE2 can be tailored to be used with any type of project


B.

A technically complex project should NOT tailor PRINCE2


C.

The tailoring of PRINCE2 is MOST appropriate for agile projects


D.

A project which is part of a programme should NOT tailor PRINCE2


Expert Solution
Questions # 60:

In which process is the work to be done assigned to a team manager?

Options:

A.

Directing a project


B.

Managing a stage boundary


C.

Controlling a stage


D.

Managing product delivery


Expert Solution