Questions # 41:

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?

Options:

A.

Increase the frequency of checkpoint reports


B.

Allow the team manager more flexibility to exceed cost tolerance


C.

Increase the frequency of event-driven controls


D.

Increase the frequency of escalations by the team manager


Expert Solution
Questions # 42:

What is an advantage of applying the 'learn from experience' principle?

Options:

A.

It allows the project board to delegate cost tolerances to the project manager


B.

It allows the project team to fully understand their roles and responsibilities


C.

It allows the project manager to delegate time tolerances to the team managers


D.

It allows the project team to identify improvements to be made during the project


Expert Solution
Questions # 43:

Identify the missing words in the following sentence.

Project assurance personnel [ ? ] the project manager.

Options:

A.

are able to overturn the decisions of


B.

must be accountable to


C.

should support


D.

report to the project board and


Expert Solution
Questions # 44:

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer


B.

Stage length is influenced by project board availability


C.

A higher level of major risk will require a stage to be shorter


D.

Use of management stages represents a time driven control


Expert Solution
Questions # 45:

Why does the project board review the PID during an end stage assessment?

Options:

A.

To confirm that project controls are adequate for the remainder of the project


B.

To notify the commissioning organization that the project has been authorized


C.

To review summarized progress to date and decide what to do next with the project


D.

To ensure that post-project reviews of operational performance are planned


Expert Solution
Questions # 46:

How often should the 'controlling a stage' process be used during a project?

Options:

A.

Once, for the whole project


B.

For each delivery stage in the project


C.

Whenever the project board meets


D.

Twice, for initiation and for the rest of the project


Expert Solution
Questions # 47:

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required


B.

By providing the tolerances for the project manager’s objectives


C.

By providing roles descriptions for the project management team


D.

By providing the justification for the project


Expert Solution
Questions # 48:

Which is 3 purpose of the ‘plans! practice?

Options:

A.

To enable an event that requires project management consideration to be controlled


B.

To provide the standards against which the project products can be quality controlled


C.

To provide the basis of control against which a project's progress can be monitored


D.

To enable control of opportunities and threats, that could Impact on delivery of the business objectives


Expert Solution
Questions # 49:

According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?

Options:

A.

One


B.

Two


C.

Three


D.

Six


Expert Solution
Questions # 50:

How does the ‘managing product delivery’ process achieve its purpose?

Options:

A.

By agreeing requirements for how project work should be undertaken


B.

By producing highlight reports to enable the project board to oversee the work


C.

By requiring the project manager to produce and monitor team plans


D.

By escalating issues and risks that cannot be resolved within stage tolerance


Expert Solution