PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 45 Topic 5 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 45 Topic 5 Discussion

Prince2-Foundation Exam Topic 5 Question 45 Discussion:
Question #: 45
Topic #: 5

Why does the project board review the PID during an end stage assessment?


A.

To confirm that project controls are adequate for the remainder of the project


B.

To notify the commissioning organization that the project has been authorized


C.

To review summarized progress to date and decide what to do next with the project


D.

To ensure that post-project reviews of operational performance are planned


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.