PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 44 Topic 5 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 44 Topic 5 Discussion

Prince2-Foundation Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

Which statement about the length of management stages in a project is CORRECT?


A.

A higher level of major risk will require a stage to be longer


B.

Stage length is influenced by project board availability


C.

A higher level of major risk will require a stage to be shorter


D.

Use of management stages represents a time driven control


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.