Prince2-Foundation Exam Topic 5 Question 46 Discussion:
Question #: 46
Topic #: 5

How often should the 'controlling a stage' process be used during a project?


A.

Once, for the whole project


B.

For each delivery stage in the project


C.

Whenever the project board meets


D.

Twice, for initiation and for the rest of the project