According to the ‘defined roles and responsibilities’ principle, how many categories of stakeholder interest need to be represented in the project management team?
According to the ‘defined roles and responsibilities’ principle in PRINCE2®, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project’s outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: PRINCE2® Foundation ManualAccording to the ‘defined roles and responsibilities’ principle in PRINCE2®, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project’s outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: PRINCE2® Foundation Manual
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit