PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 41 Topic 5 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 41 Topic 5 Discussion

Prince2-Foundation Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which action should the project manager take to ensure effective progress management when a team manager is inexperienced?


A.

Increase the frequency of checkpoint reports


B.

Allow the team manager more flexibility to exceed cost tolerance


C.

Increase the frequency of event-driven controls


D.

Increase the frequency of escalations by the team manager


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.