Prince2-Foundation Exam Topic 5 Question 40 Discussion:
Question #: 40
Topic #: 5

Which process provides information for the project board to review an updated project plan?


A.

Initiating a project


B.

Controlling a stage


C.

Directing a project


D.

Managing a stage boundary