PRINCE2® requires that the business case be formally verified by the project board at stage boundaries. This verification is essential to ensure that the project remains viable and desirable from a business perspective. The project board's review of the business case at these critical points helps in deciding whether the project should continue into its next stage.References: PRINCE2® Foundation Manual