Questions # 101:

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options:

A.

project cost tolerance


B.

stage cost tolerance


C.

Work Package cost tolerance


D.

product cost tolerance


Expert Solution
Questions # 102:

Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

Options:

A.

Principles


B.

Themes


C.

Processes


D.

Techniques


Expert Solution
Questions # 103:

Which two roles are linked by the Managing Product Delivery process?

Options:

A.

Corporate or programme management and Project Board


B.

Project Board and Project Manager


C.

Project Manager and Team Manager


D.

Team Manager and external supplier


Expert Solution
Questions # 104:

Which statement defines a risk?

Options:

A.

A certain event occurring in the future that will have a negative impact on the project's objectives


B.

An event that has already occurred that the Project Manager must deal with immediately


C.

An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives


D.

An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response


Expert Solution
Questions # 105:

What is an off-specification?

Options:

A.

A new requirement


B.

A quality tolerance


C.

A type of issue


D.

A major risk


Expert Solution
Questions # 106:

The project board needs to review whether the investment remains justified as the project progresses according to plan.

Which principle is being applied by the ‘business case' practice when the project board undertakes this review?

Options:

A.

Manage by exception


B.

Manage by stages


C.

Focus on products


D.

Tailor to suit the project


Expert Solution
Questions # 107:

Which plan is used to organize and control the work when executing a work package?

Options:

A.

team plan


B.

A stage plan


C.

A project plan,


D.

An exception plan


Expert Solution
Questions # 108:

Which is the definition of a requirement?

Options:

A.

A need or expectation that has been documented in an approved management product


B.

An event relevant to the project that requires project management consideration


C.

A prediction about future performance made by studying historical data and past patterns


D.

An uncertain event that, should it occur, will have an effect on the project.


Expert Solution
Questions # 109:

What is a description of a leadership activity within a project?

Options:

A.

Understanding and working with different departments outside of the project team


B.

Agreeing a work package with a team manager to deliver products using specific tools


C.

Ensuring that a co-located project team uses the agreed communication methods


D.

Creating a stage plan and product descriptions for the products to be created in the next stage


Expert Solution
Questions # 110:

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?

Options:

A.

Managing product delivery


B.

controlling a stage


C.

Managing a stage boundary


D.

closing a project