PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 100 Topic 11 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 100 Topic 11 Discussion

Prince2-Foundation Exam Topic 11 Question 100 Discussion:
Question #: 100
Topic #: 11

In what process is the authorization to deliver the project's products given?


A.

Starting up a Project


B.

Initiating a Project


C.

Managing a Stage Boundary


D.

Directing a Project