Questions # 131:

During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?

Options:

A.

Rework the iteration scope to accommodate these requirements.


B.

Add these requirements into the product backlog for future consideration.


C.

Raise the discovery of these requirements as an issue, and escalate to management.


D.

Immediately start working on these requirements.


Expert Solution
Questions # 132:

An agile coach is working on a digital transformation project. The project team is in the middle of a 5-week sprint. The agile coach notices constant arguing among team members on what should be the preferred technical approach to solve a current business problem. What can the agile coach do to promote collaboration and consensus-building among team members?

Options:

A.

Work with team members to resolve the issue.


B.

Escalate the issue to the product owner.


C.

Allow team members to resolve the issue.


D.

Escalate the issue to senior management.


Expert Solution
Questions # 133:

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?

Options:

A.

Work breakdown structure


B.

Description of all features' functions and an estimate of their cost


C.

Priority list of desired features and functions


D.

Comprehensive schedule of immediate deliverables


Expert Solution
Questions # 134:

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, the junior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

An agile lead is working with a team to deliver a new product. During a sprint, a junior team member has been taking too long to deliver a story. During daily coordination meetings, thejunior team member does not mention any impediments they might be facing. Senior team members realize the delay but remain quiet. During a one-to-one conversation, the agile lead discovers the junior team member is struggling with a technical issue but feels too intimidated to ask for help.

What should the agile lead do?

Options:

A.

Escalate the issue to the functional manager and request another team member with more experience.


B.

Ask the team to refer to the team charter on how to resolve this kind of impediment and help the team member.


C.

Coach the team by reminding them that a self-managed team requires everyone to be able to remove their impediments.


D.

Remind them that self-managed teams require everyone to be honest and supportive of one another to resolve impediments.


Expert Solution
Questions # 135:

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories What should the scrum master do?

Options:

A.

Ask the lead developer to identify a solution, and then share the details with the team


B.

Ask a technical manager or architect to determine a solution to the problem


C.

Work with the product owner to add a spike to the next sprint to identify a solution


D.

Create a collaborative team environment so that the team can explore a solution together


Expert Solution
Questions # 136:

A scrum team is experiencing lengthy discussions leading to no concrete actions during their scrum events. The scrum master determines that these inefficient meetings are producing waste.

What should the scrum master do to make the meetings more efficient?

Options:

A.

Issue fixed agendas and a decision log for all scrum events to ensure that only relevant agenda points are discussed and decisions are appropriately captured.


B.

Remind the team of the purpose of each scrum event, and implement a policy that long conversations deviating from the scope of each event will be stopped.


C.

Ask the product owner to conduct these discussions in individual meetings with the team members.


D.

Remind the team that staying on topic during meetings is part of being a self-managing team.


Expert Solution
Questions # 137:

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project


B.

Write backlog items that include QA as part of the description


C.

Ask for the current QA documents and incorporate them into the technical debt backlog


D.

Ask the product owner to write tests and QA controls into the acceptance criteria


Expert Solution
Questions # 138:

A product owner wants to create a release plan given the team is working in a chaotic environment. They want to set expectations about what is likely to be developed and in what timeframe for some of the stakeholders.

What should the product owner include in the release plan to achieve this?

Options:

A.

The objective, iterations and underlying features, iteration timelines, other pre-release activities, dependencies, and responsible team.


B.

The key objectives and a brief description of each user story to be delivered in each iteration release timelines and release dependencies


C.

The developer who will work on a specific feature and key DevOgs engineering activities to be performed during each iteration for the code integration.


D.

The sequence of user stories to be developed in each iteration, along with their start and end timelines, dependencies, and responsible team.


Expert Solution
Questions # 139:

If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?

Options:

A.

Project sponsor and project team


B.

Scrum master


C.

Product owner


D.

Stakeholders and project team


Expert Solution
Questions # 140:

Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.

What should the team do?

Options:

A.

Plan for overtime, and include the effort as part of the estimation.


B.

Increase team velocity to deliver more story points.


C.

Identify the reason for over-commitment to the sprint and create an action plan for the following sprint.


D.

Add resources to assist with sprint execution.


Expert Solution