During an iteration, an agile team discovers infrastructure requirements that were not initially considered. What should the team do to effectively manage this?
A.
Rework the iteration scope to accommodate these requirements.
B.
Add these requirements into the product backlog for future consideration.
C.
Raise the discovery of these requirements as an issue, and escalate to management.
Chosen Answer: