PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 130 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 130 Topic 14 Discussion

PMI-200 Exam Topic 14 Question 130 Discussion:
Question #: 130
Topic #: 14

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?


A.

Conduct a workshop for all key stakeholders to analyze the case and decide on the proper approach.


B.

Suggest an approach that was successful in a previous project.


C.

Accept the manager's suggestion and avoid unnecessary conflicts and delays.


D.

Work with the team to analyze the market opportunity and create a tailored agile approach if needed