PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 139 Topic 14 Discussion

PMI Agile Certified Practitioner (PMI-ACP) PMI-200 Question # 139 Topic 14 Discussion

PMI-200 Exam Topic 14 Question 139 Discussion:
Question #: 139
Topic #: 14

If an individual is working on a project team in a phase delivering an increment, according to the definition of done (DoD), who was that defined by?


A.

Project sponsor and project team


B.

Scrum master


C.

Product owner


D.

Stakeholders and project team


Get Premium PMI-200 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.