Question #: 133
Topic #: 14

A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.

What should the product owner have the customer review and approve?


A.

Work breakdown structure


B.

Description of all features' functions and an estimate of their cost


C.

Priority list of desired features and functions


D.

Comprehensive schedule of immediate deliverables