Pass the APM Project Fundamentals Qualification APM-PFQ Questions and answers with CertsForce

Viewing page 3 out of 13 pages
Viewing questions 21-30 out of questions
Questions # 21:

How is the deployment baseline used throughout the project?

Options:

A.

Progress monitoring and implementation of change control.


B.

Benefits realisation.


C.

Identify options for deployment.


D.

Prepare users for delivery of the output into operation.


Expert Solution
Questions # 22:

Which of the following would be considered most important when carrying out A. detailed evaluation of a change?

Options:

A.

Impact of change on baseline, risks and business case.


B.

The number of extra people required to deliver the change.


C.

How the change will be reported when it is implemented into the project.


D.

The configuration requirements Of the change when implemented into the project,


Expert Solution
Questions # 23:

Which one of the following is a generic project management process?

Options:

A.

Risk management.


B.

Learning and closing.


C.

Staff appraisal.


D.

Quality management.


Expert Solution
Questions # 24:

Which of the following is the responsibility of a project manager?

Options:

A.

Ensuring a project is aligned to the organisation's strategy.


B.

Focusing on project benefits and aligning priorities.


C.

Achieving the project's success criteria.


D.

Improving process, tools and techniques used in a project


Expert Solution
Questions # 25:

A project is typically defined in terms of scope, time, cost and which other parameter?

Options:

A.

Benefits.


B.

Quality.


C.

Tolerance.


D.

Controls.


Expert Solution
Questions # 26:

Which one of the following illustrates why effective project management is beneficial to an organisation?

Options:

A.

It utilises resources as and when required under direction of a project manager.


B.

It advocates employing A. consultancy firm which specialises in managing change.


C.

It recommends using only highly skilled people in the project team.


D.

It ensures that the chief executive is accountable for the achievement of the defined benefits.


Expert Solution
Questions # 27:

Which of the following phases precedes feasibility in an iterative project life cycle?

Options:

A.

Foundations.


B.

Pre-project.


C.

Concept.


D.

Initiation.


Expert Solution
Questions # 28:

To develop and establish a proper communication plan within a project, the project manager needsto consider which type of analysis?

Options:

A.

Budget.


B.

Stakeholder.


C.

Resource.


D.

Schedule


Expert Solution
Questions # 29:

Which of the following is the correct sequence for the stages of a linear project life cycle?

Options:

A.

Deployment, Concept, Definition, Transition.


B.

Concept, Transition, Definition, Deployment.


C.

Concept, Definition, Deployment, Transition.


D.

Transition, Definition, Deployment, Concept


Expert Solution
Questions # 30:

Which one of the following best describes stakeholders?

Options:

A.

Anyone who has heard about the project.


B.

Anyone who has an opinion about how the project should be managed.


C.

People wanting to be members of the project team.


D.

People who are affected by the project in some way.


Expert Solution
Viewing page 3 out of 13 pages
Viewing questions 21-30 out of questions