Pass the APM Project Fundamentals Qualification APM-PFQ Questions and answers with CertsForce

Viewing page 9 out of 13 pages
Viewing questions 81-90 out of questions
Questions # 81:

The definition of benefits management includes which key activities?

Options:

A.

Planning, analysis and integration of project benefits.


B.

Justification, validation and acceptance of project benefits.


C.

Identification, tracking and realisation of project benefits.


D.

Realisation, acceptance and integration of project benefits


Expert Solution
Questions # 82:

The project management plan is best described as a reference document that confirms:

Options:

A.

the project completion date as agreed between the project sponsor, other stakeholders and the project manager.


B.

the agreement between the project sponsor, other stakeholders and the project manager.


C.

the key project milestones as agreed between the project sponsor, other stakeholders and the project manager.


D.

the project start date as agreed between the project sponsor, other stakeholders and the project manager


Expert Solution
Questions # 83:

What is the main reason for having an extended life cycle?

Options:

A.

Allow the project to have extra time to ensure that that there is enough capacity to realise benefits.


B.

Allow upfront planning for any supplemental activities and incorporate additional considerations for benefits realisation.


C.

Allow time for stakeholders to decide how they will use the output to best effect that will realise benefits.


D.

Allow extra funding to be applied to the project to ensure that sufficient resources exist to maximise benefits realisation.


Expert Solution
Questions # 84:

Configuration management would be used to:

Options:

A.

ensure the required materials are in stock when needed.


B.

help the impact Of a change request to be fully assessed.


C.

help configuration within IT projects.


D.

ensure that a work breakdown structure can be completed.


Expert Solution
Questions # 85:

The responsibility for development and production of the business case is primarily with:

Options:

A.

the project manager


B.

jointly shared between the project manager and project sponsor.


C.

the project sponsor.


D.

the project steering group/committee.


Expert Solution
Questions # 86:

The main aim of a project risk management process should be to:

Options:

A.

identify project risks and then manage them appropriately.


B.

identify all project risks and transfer them immediately.


C.

identify all the things that are threats or opportunities on a project.


D.

satisfy the organisation's project management process.


Expert Solution
Questions # 87:

What information would you not expect to see in a project management plan?

Options:

A.

Quality management plan.


B.

Financial feasibility analysis.


C.

Risk management plan.


D.

Details of scope.


Expert Solution
Questions # 88:

What is a likely benefit of re-estimating throughout the project life cycle?

Options:

A.

The project will be much more economically viable.


B.

The business case is justified to a greater degree.


C.

Overall project duration is reduced.


D.

Reduction in contingency reserves are achieved.


Expert Solution
Questions # 89:

Which one of the following statements is true?

Options:

A.

Business-as-usual activities cannot be improved.


B.

Business-as-usual activities are more difficult to manage than projects.


C.

Projects are transient endeavours that bring about change to business-as-usual.


D.

A project is always the starting point for operation refinement.


Expert Solution
Questions # 90:

Which one of these categories would best represent project issues?

Options:

A.

Uncertain events that may or may not occur.


B.

Opportunities that occur through change control.


C.

Problems that the project manager has to deal with on a day-to-day basis.


D.

Threats to the project which cannot be resolved by the project manager.


Expert Solution
Viewing page 9 out of 13 pages
Viewing questions 81-90 out of questions