Questions # 121:

In project management quality is best defined as:

Options:

A.

inspection, testing and measurement.


B.

reviews and audits.


C.

fitness for purpose of deliverables.


D.

professionally-bound project reports.


Expert Solution
Questions # 122:

The main purpose of configuration management is to:

Options:

A.

minimise the impact of changes on the scope of the project.


B.

ensure that the final product meets the strategic needs of the business.


C.

provide control of the deliverables and avoid mistakes or misunderstandings.


D.

maximise the impact of agreed enhancements on the project deliverables.


Expert Solution