Questions # 31:

Which one of the following statements is true?

Options:

A.

Independent reviews and quality audits form part of quality assurance to ensure the project manager delivers on time and to budget.


B.

Quality assurance provides confidence to stakeholders that requirements for quality will be exceeded.


C.

Quality control verifies that the project deliverables conform to specification, are fit for purpose and meet stakeholder expectations.


D.

Quality planning enables the project manager to manage the trade-off between customer expectations and budget.


Expert Solution
Questions # 32:

Which structure shows the reporting relationships and communications channels for a project?

Options:

A.

Work Breakdown Structure.


B.

Organisational Breakdown Structure.


C.

Product Breakdown Structure.


D.

Responsibility assignment structure.


Expert Solution
Questions # 33:

The deployment baseline is the ______ for progress monitoring.

Options:

A.

decision gate.


B.

starting point.


C.

end point.


D.

outline schedule.


Expert Solution
Questions # 34:

In project management, the term quality is best defined as:

Options:

A.

inspection, testing and measurement.


B.

reviews and audits.


C.

fitness for purpose of deliverables.


D.

professionally-bound project reports.


Expert Solution
Questions # 35:

Which one of the following statements is true?

Options:

A.

The business case is owned by the sponsor and is created during the concept phase of the project life cycle.


B.

The business case is owned by the project manager and is created during the concept phase of the project life cycle.


C.

The business case is owned by the sponsor and is created during definition phase of the project life cycle.


D.

The business case is owned by the project manager and is created during the definition phase of the project life cycle.


Expert Solution
Questions # 36:

The phases of a project life cycle are:

Options:

A.

starting, planning, control and closing.


B.

concept, definition, development, handover and closure.


C.

initiation, definition, planning, monitoring and operations.


D.

concept, definition, implementation and operations.


Expert Solution
Questions # 37:

To be considered effective. how should quality management be used in the project?

Options:

A.

To ensure compliance.


B.

To ensure quality standards are met.


C.

To ensure the required process needs of stakeholders are met.


D.

To ensure both the project outputs and the processes meet the required needs of stakeholders.


Expert Solution
Questions # 38:

In developing a network the first task after listing the activities is to...

Options:

A.

Define activity durations


B.

Determine float


C.

Determine the interdependencies of activities


D.

Harmonise the activity to a calendar


Expert Solution
Questions # 39:

To be fully effective, the project manager:

Options:

A.

must take into consideration the internal and external environments.


B.

need only deal with the internal environment since the sponsor will deal with the external environment.


C.

should manage the external stakeholders and external environment.

D must liaise with regulating bodies to ensure requirements include the latest legislation.


Expert Solution
Questions # 40:

Which one of the following is NOT a function of leadership?

Options:

A.

Reinforcing positive relationships.


B.

Inspiring the individual.


C.

Maintaining constant tight control.


D.

Promoting the project vision.