Questions # 71:

Why is environmental analysis the most important analysis for an organisation to undertake?

Options:

A.

It allows the detailed execution plans, to be defined, that are likely to be developed in order to deliver the project.


B.

It is the only way in which the scope of the project can be identified and detailed in plans.


C.

It identifies the problems, opportunities or business needs which may require some degree of response.

D It is the only form of detailed planning that can be carried out in the earliest phases of the project life cycle.


Expert Solution
Questions # 72:

A procurement strategy is a:

Options:

A.

technical specification.


B.

day-to-day requirement.


C.

detailed timetable.


D.

high-level approach.


Expert Solution
Questions # 73:

A key aspect of managing a project involves:

Options:

A.

defining which operational systems to put in place.


B.

identifying routine tasks.


C.

ensuring ongoing operations are maintained.


D.

planning to achieve defined objectives.


Expert Solution
Questions # 74:

Which of the following statements describes a key difference between quality assurance and quality control?

Options:

A.

Quality control is about fitness for purpose whilst quality assurance is about management confidence.


B.

Quality control is about testing whilst quality assurance is about planning.


C.

Quality control is about fitness for purpose whilst quality assurance is about testing.


D.

Quality control is about management whilst quality assurance is about controlling change.


Expert Solution
Questions # 75:

The process that evaluates overall project performance to provide confidence is called:

Options:

A.

quality assurance.


B.

quality planning.


C.

quality control.


D.

quality audit.


Expert Solution
Questions # 76:

Once a proposed change is logged it should then be:

Options:

A.

accepted, rejected or deferred.


B.

accepted and the project plan updated.


C.

sent to the project sponsor for approval.


D.

assessed to determine its potential impact.


Expert Solution
Questions # 77:

Which of the following activities is not in an extended project life cycle?

Options:

A.

Deployment.


B.

Termination.


C.

Adoption.


D.

Transition.


Expert Solution
Questions # 78:

Scheduling can best be defined as the process used to determine:

Options:

A.

overall project duration.


B.

project cost.


C.

the project management plan.


D.

sub-contractor's responsibilities


Expert Solution
Questions # 79:

The risk management process is concerned with managing which of the following?

Options:

A.

Threats and opportunities.


B.

Risks and issues.


C.

Issues that have arisen.


D.

Risk events with negative impact.


Expert Solution
Questions # 80:

What is likely to be a benefit to a project of having a communication plan?

Options:

A.

The project is more likely to finish on time.


B.

There will be greater adherence to the organisation's governance and standards.


C.

The project will be less susceptible to uncontrolled change.


D.

There will be more focus on what benefits the project will be delivering.


Expert Solution