APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 85 Topic 8 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 85 Topic 8 Discussion

APM-PFQ Exam Topic 8 Question 85 Discussion:
Question #: 85
Topic #: 8

The process that evaluates overall project performance to provide confidence is called:


A.

quality assurance.


B.

quality planning.


C.

quality control.


D.

quality audit.


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.