APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 86 Topic 8 Discussion

APM Project Fundamentals Qualification (PFQ) APM-PFQ Question # 86 Topic 8 Discussion

APM-PFQ Exam Topic 8 Question 86 Discussion:
Question #: 86
Topic #: 8

Once a proposed change is logged it should then be:


A.

accepted, rejected or deferred.


B.

accepted and the project plan updated.


C.

sent to the project sponsor for approval.


D.

assessed to determine its potential impact.


Get Premium APM-PFQ Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.