Question #: 81
Topic #: 8

Why is environmental analysis the most important analysis for an organisation to undertake?


A.

It allows the detailed execution plans, to be defined, that are likely to be developed in order to deliver the project.


B.

It is the only way in which the scope of the project can be identified and detailed in plans.


C.

It identifies the problems, opportunities or business needs which may require some degree of response.

D It is the only form of detailed planning that can be carried out in the earliest phases of the project life cycle.