Pass the APM Project Fundamentals Qualification APM-PFQ Questions and answers with CertsForce

Viewing page 6 out of 13 pages
Viewing questions 51-60 out of questions
Questions # 51:

The combination of which two structures creates the responsibility assignment matrix (RAM)?

Options:

A.

OBS and CBS.


B.

OBS and WBS.


C.

PBS and CBS.


D.

WBS and CBS.


Expert Solution
Questions # 52:

Understanding who stakeholders are and their needs is a key duty of

Options:

A.

the quality manager.


B.

the key users,


C.

the project manager.


D.

the business sponsor.


Expert Solution
Questions # 53:

Which one of the following statements is true?

Options:

A.

Risk events always have beneficial effects on the project.


B.

Risk events can have either beneficial or detrimental effects on the project.


C.

Risk events always have detrimental effects on the project.


D.

Risk events have neither beneficial nor detrimental effects on the project.


Expert Solution
Questions # 54:

When delivering a project the Project Manager has to balance which one of the following constraints:

Options:

A.

definition and delivery.


B.

time, cost and quality.


C.

cost and scope.


D.

budget, spend and contingency


Expert Solution
Questions # 55:

Which one of the following best describes the purpose of a project's business case?

Options:

A.

A statement of what the project will deliver in terms of products/deliverables and satisfaction.


B.

The reasons why the project sponsor wants their project to proceed.


C.

A statement on how the project fits into the long-term aims of the project sponsor.


D.

Provides justification for undertaking the project, in terms of evaluating the benefits, cost and risks


Expert Solution
Questions # 56:

Which one of the following statements about the project life cycle is true?

Options:

A.

The phases in the project life cycle are always the same size.


B.

The same processes are used in each of the project life cycle phases.


C.

The project life cycle has a number of distinct phases.


D.

The project budget is divided equally between each phase of the project life cycle.


Expert Solution
Questions # 57:

Which one of the following is the correct definition of an issue?

Options:

A.

Any major problem that the project team has to deal with.


B.

A. problem that is the responsibility of the Project Manager.


C.

An uncertain event that should it occur would have an effect on project objectives.


D.

A. threat to project objectives that cannot be resolved by the Project Manager.


Expert Solution
Questions # 58:

Which of the following statements about risks and issues is correct?

Options:

A.

Issues must be escalated to the project sponsor.


B.

Risks must be escalated to the project sponsor.


C.

Issues must be dealt with by the governance board.


D.

Risks must be dealt with by the governance board.


Expert Solution
Questions # 59:

One of the reasons a project life cycle is split into phases is to:

Options:

A.

facilitate formal go/no-go decision making during the project.


B.

balance the costs of work in each phase of project development.


C.

mirror the major deployments of resources throughout the project.


D.

chunk work into time periods of similar durations.


Expert Solution
Questions # 60:
Options:

A.

Cost Breakdown Structure (CBS) shows costs assigned to:


B.

individual work packages using the Work Breakdown Structure (WBS).


C.

individual resources using the Work Breakdown Structure (WBS).


D.

individual resources using the Responsibility Assignment Matrix (RAM).


E.

individual deliverables using the Responsibility Assignment Matrix (RAM)


Expert Solution
Viewing page 6 out of 13 pages
Viewing questions 51-60 out of questions